Research

NETC  Annual Research Program Schedule

 

1. Research Problem Statement (RPS) Solicitation ‐ due January 16
2. Literature Search Performed on RPSs ‐ due March 20
3. Ranking of the RPSs ‐ April 15
4. Technical Committees (TC) Formed ‐ names due June 3
5. Scope of Work written by TCs ‐ due July 11
6. Scope of Work approved by Advisory Committee (AC) ‐ due August 26
7. RFP Solicitation ‐ Proposals due October 10
8. Review of Proposals by TCs ‐ recommendations to AC due November 14
9. Recommendations approved by AC ‐ due January 27
10. Execute Research Contract with PI ‐ due March 13

 

Note: Dates are subject to change based on NETC Advisory Committee input.